bj4
Home News Industry News Request A Quote for A Complete New Motor Control Center Installation
Technical Guide · Low Voltage Switchgear

How to request a complete new motor control center installation quote: the site facts, the factory and site split, and the lines that make two bids comparable.

Motor Control Center

A complete new motor control center installation is not one delivery. The factory builds it in sections, and somebody else joins those sections on site.

That split is where installation quotes differ. The guide below covers what a complete quotation has to name. It also covers where the work passes to a medium voltage motor control center supplier.

Key Takeaways

  • Complete is a claim about site work. Two quotes for one motor list differ mainly in who works after delivery.
  • The shipping split sets the site cost. Sections that travel apart need joints, lifting and a written plan.
  • Ask for four priced groups, not one lump. Equipment, transport, site assembly and verification carry different risks.
  • Site facts decide the rest. Access, floor loading and cable route change the price more than the motor list.
  • Compare against one scope sheet. Two bids only compare when both answer the same questions.

Why a complete motor control center installation is a site work document

A complete installation quote is really a site work document. The equipment is the easy half to price, because every bidder counts the same buckets.

The hard half comes after the lorry leaves. Lifting, jointing, cabling, testing and the handover of records all land on a site team.

An mcc motor control center quoted as one lump figure hides that half. Ask for the two halves separately and both become visible.

i
Complete means somebody lifts it.Ask who unloads the sections, who bolts them down and who joints the busbar. Those three answers move the price far more than the motor list does.

The shipping split is the line that decides your site cost

No factory ships a finished lineup as a single unit. A motor control centre built in sections leaves in road legal units, and the joints wait for site.

The shipping split names where those cuts fall. It sets how many units travel, how many joints are made on site, and what each unit weighs.

The weight decides the crane, and the crane decides the access route. Ask for the split drawing with the quotation. A bid without one is priced against a delivery nobody has planned. A withdrawable switchgear lineup of eight sections is where that gap gets expensive.

Factory work a row of low voltage switchgear sections standing side by side on a factory floor, each one a separate unit for shipping
What travels

Sections, not one cabinet

The row above is several separate units, not one box.

Each unit travels alone and is joined on site.

Where the factory hands the assembly over to your installer

The handover point should be written down, not assumed. Most disputes on a new installation are about a cable nobody terminated.

Four groups of priced work belong in every complete quotation. You can buy the motor control center manufacturers group, and the other three come from other crews. That is normal, and it is not a sign of a weak bid.

The four groups of priced work in a new installation
Priced groupWhat it coversWho normally does it
The assemblySections, buckets, busbar, internal wiring, factory testsThe motor control center manufacturer
Transport and civil workFreight, offloading, floor preparation, fixingsThe buyer or the installer
Site assemblyPositioning, bolt down, joints between sections, cablingThe installer
VerificationInsulation and continuity tests, commissioning, recordsShared, and it must be named

An industrial motor control center quote that merges all four cannot be scored. Split them, and you can see which bidder is quietly buying the site risk. The assembly itself is built and verified to IEC 61439. That is the standard a factory test record refers to.

Room, floor and route: the site facts the factory never sees

The factory never sees your room, and that gap is where surprises start. Photographs and dimensions close most of it in one page.

Three facts move the price most often. The door and the turning space, the floor the sections sit on, and the route the cables take.

a switchgear cabinet with its door open showing the breaker row and the cable space beneath, standing on a factory floor
Send these four

The site facts that change the price

1
The door and the turning space.A section on a pallet needs a route in and a clear place to be set down.
2
The floor and its loading.A raised floor or a weak slab changes how the cabinet is fixed down.
3
The cable route.A trench, a top entry or a bottom entry decides how much site cabling is left over.
4
The room conditions.A hot, damp or dusty room changes the enclosure and the cooling.

What to send with the request so the price comes back real

A vague enquiry returns a vague price. A short pack is enough to price a complete installation honestly.

Send the motor list with ratings, quantities and starting duty. A motor control bucket with a heavy duty start is not priced like a light one. The motor list is where that shows.

Then send the single line diagram, including the incoming device and its rating. Add the room drawing with the access route, plus the delivery address and the site conditions.

A motor control center manufacturer can price the rest from those. A vfd panel quoted as one bucket has to start with the drive rating. The same logic runs through every bucket in the lineup.

Factory wiring a row of current transformers and green terminal blocks wired on a mounting plate inside a control panel
Inside the sections

The wiring the factory finishes

The current transformers and terminal blocks above are factory work.

The cables leaving those terminals are site work.

!
Do not accept one lump figure.A single number cannot be compared with another single number. Ask every bidder to price the same four groups on the same sheet.

Where the low voltage lineup ends and the high voltage one begins

Most motor control work sits below one kilovolt. That is the low voltage motor control center world, and the design there is settled.

Above roughly one kilovolt the shape changes. The incomer becomes a breaker in a metal enclosure, and the clearances widen.

So the enquiry has to say which side of the line it belongs to. A 400 V job goes to a low voltage builder. An 11 kV job goes to a medium voltage motor control center supplier. The medium voltage switchgear on that side is a different assembly altogether.

Scoring two installation quotes against one scope sheet

Two quotes only compare when both answer the same questions. Build one scope sheet and send it to every bidder.

The sheet lists the four priced groups and the shipping split. It also lists the site work you will do and the records you expect. Ask every bidder to price the motor control center mcc panel and the three site groups separately.

Then score the answers line by line. A bidder with a working ISO 9001 system names its own test records without being pushed. That habit shows up in the low voltage power distribution work it hands over.

What two installation quotes must show before they can be scored
Line on the scope sheetThe question to ask both bidders
Shipping splitHow many units travel, and what does each one weigh
Incoming interfaceWho terminates the incoming cable, and at which terminals
Outgoing interfaceWho lands the motor cables, and at which end of each run
JointingWho makes the joints between sections, and with whose kits
VerificationWhich tests are done in the works and which are repeated on site
RecordsWhich drawings, lists and certificates arrive with the assembly
v
Reuse the same scope sheet.The second installation should be scored with the first sheet. A bidder who learns your sheet quotes the next job faster and with fewer assumptions.

Frequently asked questions

What does complete mean in a motor control center quote?
It should mean the assembly arrives joined and verified, with the site work named. Ask each bidder to write down who unloads, who positions and who makes the joints between sections. If those three answers are missing, the bidder has priced equipment and left the site work to you.
How is a new motor control center installation priced?
It is priced in four groups: the assembly, transport and civil work, site assembly, and verification. The assembly is the only group a factory can price alone. Ask for all four as separate lines. The other three are where two quotes for the same motor list start to differ.
Who supplies the cables between the sections?
Usually the installer, but the kit for the joints between sections often comes from the factory. Write it into the order either way. A gap here is the most common cause of a stalled installation. The crew arrives and the interconnecting kit is still on a lorry.
When does a job need a medium voltage motor control center instead?
When the motors or the incomer sit above roughly one kilovolt. Below that, a low voltage motor control center covers the whole lineup. Above it, the breaker, the clearances and the test regime all change. Send the enquiry to the right side of that line, because the two quotes cannot be compared.
What should I send with the request for a quote?
Send four things. Send the motor list with ratings and duty. Add the single line diagram with the incoming device. Then add the room drawing with the access route and the site conditions. A motor control center manufacturer can size most of the lineup from those, and the estimate stops being a guess.
How do I compare two installation quotes fairly?
Send both bidders the same scope sheet. It should name the shipping split, the incoming and outgoing interfaces, the jointing, the tests and the records. Two quotes only compare when they answer identical questions. Without that sheet you are comparing two different projects with similar names.
What should arrive with the assembly on site?
The packing list and the routine test record from the works. Add the as built drawings and a device list with part numbers. Ask for them in the purchase order rather than afterwards. A shipment without those documents costs more to maintain, because every later fault starts with an identification problem.
Can one supplier cover the equipment and the installation?
Sometimes, and only when the supplier also employs the site crew. Ask who is on site and who employs them. A trader or a motor control center mcc reseller prices the assembly and subcontracts the rest. That adds a margin and removes a direct line when something goes wrong.

Final thoughts

The quotation is the plan for the installation. Read it as four groups of work rather than one figure.

A complete mcc motor control center installation is judged on what happens after the lorry leaves. Fix the factory and site boundary before anyone prices it.

Grid and industrial load keeps growing. The IEA tracks how much of that demand lands on networks built for a smaller load.

Send the motor list, the single line diagram, the room drawing and the site conditions. Giantele engineers return a marked drawing, a shipping split and a written proposal for each group of work.

Need the factory and site split priced separately?

Send the motor list, the single line diagram, the room drawing and the access route. Giantele engineers return a marked drawing, a shipping split and a written proposal for each group of work.

Contact Giantele
GE

Giantele Engineering Team

Low voltage switchgear engineers at Zhejiang Zhegui Electric. We build IEC 61439 verified assemblies for factories, mines and utilities across Africa, the Middle East and Europe.

IEC 61439 CE ISO 9001

Get a Quote in 12 Hours

Send your project specs — our engineers reply with a verified price and IEC-compliant drawing within one working day.

MAKE AN ENQUIRY
or chat directly

+

Years

+

Countries

h

Reply
Build Your Switchgear Project with a Verified Chinese Manufacturer
Whether you are an EPC, a plant engineer, or a regional distributor — we deliver IEC-compliant low & medium voltage switchgear with full documentation, container-ready packing, and African-port logistics support.
12-hour response from our engineering team — not a sales bot.
NDA-friendly — share your single-line diagram without disclosing project name.
OEM/ODM welcome — your brand, our 13-year manufacturing backbone.
Free spec review — we flag IEC compliance gaps before you tender.
Request Engineering Consultation
MAKE AN ENQUIRY

Related Blogs

We will work with other excellent partners to deliver more high-quality products to the world.
MAKE AN ENQUIRY

Copyright © Zhejiang Zhegui Electric Co., Ltd. is founded in Zhejiang, China.   SItemap