Key takeaways
- A listing proves frame size, rating, poles and finish. It proves nothing about the assembly behind the door.
- Five documents stand in for a factory visit. Ask for all five before you discuss price.
- Busbar section and cable space decide whether the panel survives its load.
- A type test report names the assembly and the rating. A logo wall names nobody.
- Pay against an approved drawing and a routine test sheet, never against a photograph.
Buying an ATS panel online is a document exercise long before it is a transaction. The web page sells a photograph. The supplier you keep sells a drawing, a test record and a packing list.
This guide covers what a listing can prove. It lists the five documents that replace a factory visit. It also covers paying across a border without losing the deposit.
What an online listing can prove about an ATS panel
A listing can prove four things. It shows the frame size, the current rating, the pole count and the paint finish. Everything else on the page is a claim.
The heading may call it a gen switch, a changeover or a standby panel. Names change with the country and with the trade. Read the rating row, not the title.
Three photographs every seller publishes
A page that publishes only those three shots is not hiding anything sinister. It is showing what a marketing team can photograph without opening a live board.
The unit you are comparing is a generator transfer switch panel before it is a catalogue line. Two sellers can photograph the same frame and still quote two different builds.
Distance is the normal condition of this trade. The grid is thin where backup sells best. The IEA tracks how wide that gap stays, year after year. Buyers shop across borders because of it.
Five documents replace a factory visit
You will not walk the shop floor. Ask for five documents instead, and read them in this order.
- Single line diagram, marked with the changeover, the protection and the metering.
- General arrangement drawing with dimensions, cable entries and door swing.
- Nameplate schedule listing every device, its rating and its setting.
- Type test report for the assembly, naming the standard and the rating tested.
- Routine test sheet for your own unit, signed and dated after assembly.
The nameplate schedule is the one buyers skip. It is also the one that catches a missing surge arrester before the crate leaves.
Compare the drawing against the electrical switch gear it will feed. That main electrical switchboard has a fault level, a spare way count and a cable size of its own. A panel that ignores them is a panel you will modify on site.
The photo never shows the busbar or the cable space
The bars carry the rating, not the label
Copper section sets the continuous current. A 630 A frame with thin bars runs hot at 500 A.
Cable space decides whether your gland plate fits. Ask for the depth behind the door.
Ask for one photograph of the inside with the door open, and one busbar drawing. Two files answer more than twenty pages of brochure.
A low voltage switch gear assembly is verified as a whole. The bars, the clearances and the partitions belong to one test, not to a folder of component certificates. Start with IEC 61439 before you accept that folder.
Thin bars are not the only shortcut. A missing partition between the incoming and the outgoing side turns one fault into two.
Ask for the type test, not the logo wall
Logos on a front page prove nothing about the unit you receive. A type test report names the assembly, the rating and the laboratory.
The routine test comes second. It covers insulation resistance, dielectric withstand and the wiring check on your own unit.
The two files answer different questions. Type tested assemblies earn the design approval. The routine sheet covers one build, and only that build.
A supplier working under ISO 9001 can produce that sheet with a serial number on it. Ask for the number before you ask for the discount.
Most switch gear manufacturers will send a type report on request. The ones that stall for a week are telling you something about the file they do not have.
Ask who signed it. An engineer's name on a test sheet is worth more than a red stamp.
A 220 volt manual transfer switch is bought on the handle and its padlock
On a manual unit the handle is the whole mechanism. Ask what it breaks, how many operations it is rated for, and whether it locks in both positions.
A 220 volt unit usually switches one circuit. That makes it cheap, and it makes improvisation tempting. Buy the enclosure with the switch, not after it.
A handle without a padlock hole will be pulled by whoever walks past the door.
Check the contact sequence too. Changeover under load needs a break before make action, and two hands on two handles is not that.
Two ratings on one listing, and which one ships
Listings often put a thermal current and a frame size in the same row. The frame is what the enclosure can hold. The thermal rating is what it may carry all day.
Two switch gears with the same label can carry different bars, different devices and a very different price. The label is the cheapest part of the build.
| Listing line | What settles it | Question to send |
|---|---|---|
| Current rating | Busbar drawing and thermal test | Continuous current at my site ambient? |
| Pole count | Earthing design | Does the neutral break with the phases? |
| Enclosure | Site conditions | Which IP rating, and is a heater fitted? |
| Cable entry | Gland plate drawing | Top or bottom, and what bend radius? |
| Controller | Logic description | What does it do after a failed start? |
| Standard | Type test report | Which standard, which rating, which lab? |
Bids for generator switchgear rarely differ on the device itself. They differ on the bar, the partition and the test file behind it.
Six rows, six files. A seller who answers five is close to a real offer. One who answers two is a reseller with a catalogue.
Paying a supplier you have never met
Payment terms are the clearest signal of how a supplier expects the job to go.
A deposit against an approved drawing is normal in this trade. Full payment before the routine test is not, whatever the discount offered.
Pay the company named on the drawing. A personal account, a second trading name or a sudden change of bank details is a stop sign.
Ask for the test sheet before the balance. It costs one email and it settles most arguments later.
Packing, freight and who owns the damage
An electrical transfer box travels as a frame on a pallet
Sea freight means two handling points and one long humid ride. Ask for stretch film, desiccant and a wooden case.
Photograph the packing before you cut it open. A claim needs that image.
Weigh the crate against the drawing. A panel that arrives 80 kg light is missing something, and the driver will not know.
An enquiry that gets a buildable answer
One email, six lines: rating, poles, earthing, cable size, site conditions and delivery port.
You may call it a gen transfer switch. The next buyer calls the same box a transfer switch for backup generator. The drawing comes back the same either way.
Say what the load is, not what the product is called. A generator automatic transfer switch enquiry also needs the preferred changeover time.
Add the loads you refuse to shed. A hospital ward and a warehouse can share a rating and still need different priorities.
Ask for the drawing before the price. A quote without a general arrangement is a number, not an offer.
Frequently asked questions
Can I buy an ATS panel online without visiting the factory?
How do I check a supplier I have never used?
Is a manual changeover cheaper than an automatic one?
What does the type test report actually cover?
Who pays for damage in transit?
How long does delivery take?
Can the panel be built to my local standard instead?
Final thoughts
Buy the documents, then the panel. A listing proves a frame size. It does not prove the busbar inside it, or the test sheet behind it. Five files close that gap faster than any video call.
Send the single line drawing
Send the board drawing, the generator rating and the delivery port. We will come back with a priced scope and the document pack behind it.
Contact Giantele